Has any house been finished/signed off yet? I'd bring it to the developers attention, remember that if your installing the systems, it's up to you to make sure they comply with the latest requirements.In regards to new builds requiring zoning I'm working on a Cala development with a minimum of 5 bed house and not one house type is zoned. Where as the site i was on before was 1/2 bed social housing and was zoned. Zone 1 was living room, kitchen, bathroom & hall. Zone 2 bedroom. Seemed pointless to me at the time.
Yeah mate, there a into the 3rd phase with other 100 houses signed and handed over. The system is ASHP with hyprid boiler with an unvented indirect cylinder. I've not asked the agent yet but i think it's more to do with SEDBUK rating witch CH zoning obvisouly improbe as does ASHP. I'll find out more. I'm in Scotland also which might make a difference.Has any house been finished/signed off yet? I'd bring it to the developers attention, remember that if your installing the systems, it's up to you to make sure they comply with the latest requirements.
Have been sadly let down by a plumber and doing the first fix for a new build. I have questions regarding the correct procedure for chasing in pipework behind what will be dot and dabbed..
Its 3 bed bungalow with 9 radiators in total.
I was planning on running lagged plastic22mm flow / returns in the roof space to and tee off 15s for each radiator. Some of which are underneath windows.
1. How deep do you usually chase when its being dot and dabbed? And do you also just take a notch out of the wall plate?
2. Would you chase one larger channel and run both pipes in the same place?
Does the plastic need to be insulated or ducted in some way so it could potentially be removed at a later date?
3. The rads will be attached to chrome.. would compression fittings with liquid ptfe be ok to use to connect the chrome to plastic? But obvioulsy this wont be able to be removed at a later date without pulling the wall apart.
4. How would you chase it in? Straight line down the wall with an elbow at rad pipe height?
Finally anything else ive overlooked / missing? How would you usually approach this job?
Thanks in advance for any help
Reply to New build first fix help needed in the Plumbing Jobs | The Job-board area at PlumbersForums.net
We get it, advertisements are annoying!
Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.